PMP Process Practice Questions

Practice Process questions for the Project Management Professional. Every question includes a full explanation of why the correct answer is right and why the tempting distractors are wrong.

52 questions available · hard difficulty · PMP · Free, no registration required

←PMP1 / 10
0 / 0

Question Map

Current
Correct
Incorrect
Flagged
Unanswered
Q1easyProcess

A 12-month predictive fiber-optic rollout has a Budget at Completion (BAC) of $600,000. At the end of Month 6, Planned Value (PV) is $300,000, Actual Cost (AC) is $250,000, and Earned Value (EV) is $225,000. What are the Cost Performance Index (CPI) and Schedule Performance Index (SPI), and what do they indicate?

Select an answer

On the PMP · 41% of PMP exam (Domain II — largest domain, July 2026 ECO)

The largest domain on the 180-question, 240-minute PMP exam (~70 scored items), blending situational governance decisions with concise quantitative scenarios covering Earned Value Management (EVM), Critical Path Method (CPM), Expected Monetary Value (EMV), Kanban flow metrics, and procurement contracts.

What Process tests

Process tests whether you can tailor and execute technical project delivery across Predictive, Agile, and Hybrid lifecycles. Core areas include EVM cost and schedule indices (CPI, SPI, CV, SV, EAC, TCPI), critical path float and schedule compression, Scrum ceremonies, Kanban WIP limits and cycle/lead time charts, qualitative and quantitative risk responses, Integrated Change Control (CCB) versus Product Owner backlog refinement, procurement contract risk allocation (FFP, FPIF, CPFF, CPIF, T&M), and Cost of Quality.

Where test-takers lose points

Confusing an uncertain future 'risk' with a current 'issue'

Risks are uncertain future events tracked in the risk register with probability, impact, and planned responses (avoid, mitigate, transfer, accept, escalate). Once an event has already happened or blocks work today, it is an issue logged in the issue log requiring immediate assessment and resolution.

Applying Predictive CCB rules to an Agile sprint—or skipping CCB on a Predictive baseline

Changes to approved Predictive scope, schedule, or cost baselines require impact analysis and formal Change Control Board (CCB) approval. In Agile, evolving feature requests go through the Product Owner via backlog reprioritization without a CCB unless fixed contract or charter boundaries change.

Inverting EVM ratios or misassigning buyer-versus-seller procurement risk

Earned Value (EV) always comes first: CPI = EV / AC and SPI = EV / PV, so values below 1.0 signal cost overruns or schedule delays. In procurement, Firm Fixed Price (FFP) puts maximum cost risk on the seller when scope is clear, whereas Cost-Plus and Time & Materials shift cost growth risk onto the buyer.

How to practise Process

Anchor every Process question on lifecycle clues first: words like 'WBS, baseline, CCB, critical path' trigger Predictive change control, 'iteration, velocity, WIP limit, retrospective' trigger Agile flow rules, and 'regulatory gate with iterative sprints' signals Hybrid tailoring. Drill the standard Predictive change sequence—log, analyze cross-constraint impact with the team, identify options, then submit a formal change request—until you can spot skipped steps instantly.

Common questions about PMP Process

How math-heavy is Earned Value Management on the July 2026 PMP exam?

Long multi-step arithmetic is rare, but you must instantly interpret CPI = EV / AC, SPI = EV / PV, CV, SV, EAC, and TCPI in context and decide whether to crash, fast-track, or re-baseline based on budget and schedule constraints.

What is the exact trade-off between crashing and fast-tracking a schedule?

Crashing adds funded resources or overtime to critical-path tasks, increasing direct cost while minimizing added rework risk; fast-tracking overlaps critical-path tasks that were planned in sequence, saving time without extra headcount but raising rework and risk.

How do Sprint Review and Sprint Retrospective differ on Process questions?

Sprint Review inspects the working product increment with external stakeholders to adapt the product backlog, whereas Sprint Retrospective is an internal team ceremony held afterward to inspect workflow, quality practices, and working agreements.

Sample Process Questions with Answers

10 example questions with full explanations. Use the interactive practice above to work through the complete set.

Question 1easy

A 12-month predictive fiber-optic rollout has a Budget at Completion (BAC) of $600,000. At the end of Month 6, Planned Value (PV) is $300,000, Actual Cost (AC) is $250,000, and Earned Value (EV) is $225,000. What are the Cost Performance Index (CPI) and Schedule Performance Index (SPI), and what do they indicate?

  • A.Cost efficiency of 1.11 and schedule index of 0.75 show under-budget work trailing the plan.
  • B.Indices of 0.83 for cost and 0.90 for schedule show slow spending keeps funds healthy.
  • C.Efficiency sits at 0.90 for cost and 1.33 for schedule, showing overruns ahead of plan.
  • D.With CPI at 0.90 and SPI at 0.75, the project is over budget and behind schedule.✓

Correct answer: D

Cost Performance Index equals Earned Value divided by Actual Cost ($225,000 / $250,000 = 0.90), and Schedule Performance Index equals Earned Value divided by Planned Value ($225,000 / $300,000 = 0.75); values below 1.0 mean the project is over budget and behind schedule (Option D). Inverting EV/AC gives 1.11 (Option A), inverting EV/PV gives 1.33 (Option C), and comparing AC to PV ignores actual work accomplished (Option B).

Question 2medium

A predictive substation-upgrade project has a Budget at Completion (BAC) of $840,000. At a milestone review, 40% of total scope is complete, Actual Cost (AC) is $420,000, and Planned Value (PV) is $420,000. Engineering confirms that slower rock-trenching productivity is permanent across the site, so remaining work will experience the same cost efficiency rate without schedule-recovery surcharges. What is the Estimate at Completion (EAC)?

  • A.$1,050,000 using cumulative cost efficiency across the total budget✓
  • B.$672,000 multiplying budget at completion directly by the cost performance index
  • C.$1,207,500 weighting remaining work by both cost and schedule performance indices
  • D.$924,000 assuming remaining trenching reverts immediately to original budget rates

Correct answer: A

Earned Value is 40% of $840,000 = $336,000, giving CPI = $336,000 / $420,000 = 0.80. Because current cost variances are typical and expected to persist, EAC = BAC / CPI = $840,000 / 0.80 = $1,050,000 (Option A). Using $924,000 treats the rock condition as an isolated one-time variance (Option D), $1,207,500 compounds CPI * SPI (Option C), and $672,000 multiplies by CPI instead of dividing (Option B).

Question 3hard

A project network has five tasks: T1 (Start, 4 days) feeds both T2 (7 days) and T3 (3 days); T3 feeds T4 (2 days); and both T2 and T4 must finish before T5 (Finish, 5 days) can begin. If a supplier defect delays T3's duration from 3 days to 8 days, what happens to the overall project completion date?

  • A.Completion slips by 1 day to Day 17 because T3 carries 4 days of available slack.
  • B.Schedule completion extends by 3 days to Day 19 after exhausting 2-day total float.✓
  • C.Milestone Day 16 holds steady because parallel task T2 absorbs the 3-day overrun.
  • D.Delivery moves out 5 full days to Day 21 since every path starts with zero float.

Correct answer: B

Originally, path T1-T2-T5 takes 4 + 7 + 5 = 16 days (critical path) while path T1-T3-T4-T5 takes 4 + 3 + 2 + 5 = 14 days, giving T3 a total float of 2 days. Extending T3 by 5 days pushes T1-T3-T4-T5 to 19 days, consuming its 2-day float and delaying finish by 3 days to Day 19 (Option B). Computing 4 days of float omits T4 (Option A), adding all 5 days ignores existing float (Option D), and T2 cannot absorb a parallel branch overrun (Option C).

Question 4medium

A project manager uses Expected Monetary Value (EMV) to choose between two turbine-controller strategies. Refurbishing the legacy unit costs $180,000 upfront with a 30% probability of a $150,000 field-retrofit failure (70% chance of $0 extra cost). Installing a new modular unit costs $210,000 upfront with a 10% probability of a $60,000 adapter fix (90% chance of $0 extra cost). Which choice has the lower expected total cost?

  • A.Selecting the legacy refurbishment since subtracting $45,000 risk value lowers net cost to $135,000.
  • B.Installing the modular unit with $216,000 expected cost versus $225,000.✓
  • C.Refurbishing the legacy unit because its upfront capital outlay is $30,000 lower at $180,000.
  • D.Choosing the modular unit based on unweighted worst-case totals of $270,000 versus $330,000.

Correct answer: B

Expected total cost equals base cost plus probability-weighted threat cost: legacy refurbishment = $180,000 + (0.30 * $150,000) = $225,000, whereas the modular unit = $210,000 + (0.10 * $60,000) = $216,000, saving $9,000 in expected cost (Option B). Looking only at upfront outlay ignores risk exposure (Option C), subtracting threat cost reverses sign convention (Option A), and summing unweighted worst cases omits probabilities (Option D).

Question 5medium

During a hybrid rail-signaling project, a previously logged customs-inspection risk occurs: imported optical transceivers are detained at the port, blocking tomorrow's lab integration sprint. The risk register already contains an approved contingency plan using certified hardware-in-the-loop simulators. What should the project manager do FIRST?

  • A.Perform a quantitative Monte Carlo simulation to update port-delay probability distributions.
  • B.Record the detention in the issue log and trigger the pre-approved simulator contingency plan.✓
  • C.Halt lab work and wait two weeks for the monthly Change Control Board to authorize simulator use.
  • D.Add port detention as a low-priority watch-list entry for next quarter's qualitative risk review.

Correct answer: B

When an identified risk materializes into a present blocker, it becomes an issue: the project manager logs it in the issue log, updates risk status, and immediately executes the pre-approved contingency response (Option B). Running probabilistic simulations on a realized event (Option A), waiting weeks to re-approve an already authorized contingency (Option C), or parking an active blocker on a watch list (Option D) confuses risks with issues.

Question 6medium

An aerospace test program reports CPI = 1.15 and SPI = 0.84 ahead of a fixed launch-window audit. Two critical-path activities—thermal vacuum cycling and acoustic vibration testing—use the sole flight-qualified prototype, and engineers warn that running both tests simultaneously would crack the chassis. Which action should the project manager take to recover the schedule?

  • A.Eliminate three mandatory high-temperature vacuum cycles so testing finishes before the audit date.
  • B.Crash the critical-path test sequence by adding a certified second technician shift.✓
  • C.Fast-track thermal and acoustic tests in parallel on the single prototype to avoid overtime charges.
  • D.Authorize weekend overtime on non-critical user-manual formatting tasks that have eight days of float.

Correct answer: B

With healthy cost performance (CPI = 1.15) and a hard physical constraint preventing parallel testing on one prototype, crashing the sequential critical-path activities via extra certified lab shifts trades approved cost for schedule compression safely (Option B). Fast-tracking violates physical dependencies (Option C), cutting mandatory cycles sacrifices quality (Option A), and crashing float-heavy tasks achieves zero schedule gain (Option D).

Question 7hard

A quality lead on a battery-module line inspects a statistical process control chart for laser weld depth. Every plotted sample sits inside both the upper and lower control limits and inside customer specification tolerances, yet the most recent eight consecutive points all fall above the process centerline. What should the project manager conclude and do NEXT?

  • A.Investigate an assignable cause of process drift immediately because eight consecutive points above the mean violate the rule of seven.✓
  • B.Scrap the last eight production pallets immediately because points above the mean fail customer tolerances.
  • C.Recalculate wider control limits manually so the upward shift looks like random common-cause noise.
  • D.Continue production unchanged since every weld measurement remains inside control and specification limits.

Correct answer: A

Under the Rule of Seven, seven or more consecutive data points on one side of the mean—even inside control limits—indicate non-random, out-of-control process drift (such as fixture wear or laser calibration shift) requiring root-cause investigation before defects occur (Option A). Ignoring the run misses early warning signals (Option D), scrapping conforming in-spec units confuses control limits with spec limits (Option B), and widening limits hides real drift (Option C).

Question 8medium

A clean-tech program must construct highway fast-charging stations with 20-week utility transformer lead times and fixed municipal permit inspections while simultaneously evolving a driver reservation mobile app through rapid beta-user feedback. Which delivery approach should the project manager tailor?

  • A.Tailor a hybrid model coupling predictive hardware milestones with Agile mobile-app sprints.✓
  • B.Manage civil construction and software as disconnected projects with no shared integration readiness gates.
  • C.Run pure two-week Scrum sprints for civil trenching and transformer procurement without upfront schedules.
  • D.Lock all mobile app UI screens under a sequential waterfall freeze nine months before beta testing.

Correct answer: A

Tailoring a hybrid lifecycle matches each workstream's nature—predictive planning for high-cost-of-change physical permits and long-lead transformers, paired with iterative Agile sprints synchronized at integration milestones for evolving mobile software (Option A). Pure Scrum fails long-lead civil procurement (Option C), pure waterfall stifles app feedback (Option D), and uncoordinated silos break launch integration (Option B).

Question 9medium

During a risk workshop for a hospital microgrid project, the team discovers an opportunity: passing utility commissioning two weeks ahead of baseline qualifies the client for a $350,000 clean-energy incentive grant. Which TWO responses apply PMI's EXPLOIT and SHARE strategies to this positive risk? (Choose TWO.)

  • A.Partner with a certified local grid-testing specialist under a joint incentive-split contract tied to early sign-off.✓
  • B.Buy delay-in-startup insurance from an underwriter to cover liquidated damages if commissioning slips.
  • C.Skip mandatory islanding-safety tests so commissioning paperwork reaches the utility ahead of the grant deadline.
  • D.Note the grant date in the risk register without altering staffing so the client collects it if work finishes early naturally.
  • E.Dedicate the firm's master protection-relay engineers and pre-calibrated test rigs to guarantee early commissioning.✓

Correct answer: E, A

For positive risks (opportunities), Exploit removes uncertainty so the upside occurs at 100% by assigning top talent and ready equipment (Option E), while Share allocates ownership to a third-party partner best positioned to help capture the benefit via shared incentives (Option A). Insurance transfers negative threats (Option B), doing nothing is passive acceptance (Option D), and skipping safety tests breaches professional ethics (Option C).

Question 10medium

Following expensive field repairs on an earlier product generation, an industrial-robotics program wants to shift its Cost of Quality budget upstream into PREVENTION costs rather than appraisal or failure costs. Which TWO activities classify strictly as prevention costs? (Choose TWO.)

  • A.Conducting destructive torque-load audits on finished robotic arms sampled randomly from shipping lots.
  • B.Dispatching field technicians to replace overheated servo drives under customer site warranties.
  • C.Qualifying supplier manufacturing processes and calibrating CNC assembly jigs prior to production runs.✓
  • D.Training firmware and mechanical engineers on poka-yoke mistake-proofing before detailed design begins.✓
  • E.Re-machining out-of-tolerance actuator housings caught by technicians prior to final crate sealing.

Correct answer: D, C

Prevention costs build quality into the process upfront to keep defects from occurring—such as engineer mistake-proofing training (Option D) and upfront supplier process qualification plus equipment calibration (Option C). Factory rework before shipping is internal failure (Option E), finished-lot destructive sampling is appraisal (Option A), and customer warranty repairs are external failure (Option B).

More PMP practice topics

All PMP topics & study guide →Timed PMP mock exam →

Full PMP Prep Course

Official PMI

PMI Study Hall PMP Essentials by Project Management Institute (PMI)

Official PMI practice questions, full-length mock exams, and scenario drills built directly to the current PMP Examination Content Outline.

$49 / 3 moView Course →
Affiliate link — we may earn a commission at no extra cost to you. DisclosureCompare all PMP courses →