On the PMP · 33% of PMP exam (Domain I — July 2026 ECO)
Roughly 56–60 scored questions out of 180 total items in 240 minutes (170 scored, 10 unscored pretest), combining four-option situational single-choice ('What should the project manager do FIRST or NEXT?'), multiple-response (choose two or three), and drag-and-drop items across ~60% Agile/Hybrid and ~40% Predictive scenarios.
What People tests
People evaluates how effectively you lead, coach, and align project teams and stakeholders without relying on positional authority. Under the July 2026 Examination Content Outline, it covers servant leadership, psychological safety, team charters and working agreements, conflict resolution modes, emotional intelligence, mentoring underperforming contributors, distributed cross-cultural collaboration, stakeholder engagement matrices, and negotiating shared resources in matrix organizations.
Where test-takers lose points
Escalating to the project sponsor or HR before analyzing and collaborating directly
PMI treats escalation to the sponsor, steering committee, or HR as a last resort reserved for charter-level scope/budget limits or code-of-conduct violations. Always meet privately to understand root causes or facilitate team problem-solving first.
Directing a self-organizing Agile team instead of acting as a servant leader
Assigning individual tasks, overriding sprint commitments, or turning daily standups into status reports violates Agile mindset. A servant-leader PM shields the team from mid-sprint scope disruption, clears impediments, and lets the Product Owner own backlog priority.
Settling for 'compromise' or 'smooth' when 'collaborate/problem-solve' is viable
Compromise produces a lose-lose split and smoothing only masks tension temporarily. Unless an urgent safety or regulatory deadline demands unilateral action, PMI rewards confronting the root issue collaboratively using agreed ground rules from the team charter.
How to practise People
On every 'FIRST / NEXT' People stem, diagnose three signals before reading choices: delivery model (Agile, Hybrid, or Predictive), whether the friction is interpersonal or structural, and where authority sits. Eliminate punitive or pass-the-buck answers—replacing a team member, escalating immediately, or asking senior management to decide—and favor active listening, reviewing the team charter or stakeholder engagement assessment matrix, and coaching the team toward shared ownership.
Common questions about PMP People
How did the July 2026 PMP ECO change the People domain weight?
Domain I shifted from 42% in the 2021 ECO to 33% in the July 2026 ECO as Business Environment expanded to 26%, while keeping servant leadership, psychological safety, conflict resolution, and stakeholder engagement central across roughly one-third of all scored items.
How do I pick between two polite leadership answers on 'do FIRST' questions?
Follow PMI's sequence: assess and listen privately to uncover the root cause BEFORE updating plans, running a workshop, or changing processes, and collaborate directly with the person involved rather than handing the problem to a functional manager or sponsor.
Who handles a senior stakeholder demanding a new feature mid-sprint?
The project manager protects the team from mid-sprint scope disruption and guides the stakeholder to work with the Product Owner, who evaluates business value and prioritizes the item in the product backlog for an upcoming sprint.
10 example questions with full explanations. Use the interactive practice above to work through the complete set.
Question 1easy
Two senior cloud engineers on a hybrid payment-modernization project disagree sharply over API gateway rate-limiting architecture. Both engineers present valid latency benchmarks and failover data, and three days remain before the architecture baseline freeze. Which conflict-resolution approach should the project manager use?
- A.Facilitate a collaborative session to evaluate both designs against latency and failover criteria.✓
- B.Postpone the architecture discussion until next sprint so interpersonal tension cools down on its own.
- C.Split the design down the middle so each engineer gives up half of their preferred rate-limiting rules immediately.
- D.Mandate the more senior engineer's gateway architecture immediately to preserve schedule momentum.
Correct answer: A
When both engineers hold valid technical evidence and time permits before a decision deadline, collaborating (problem-solving) integrates facts against objective criteria to achieve consensus and commitment (Option A). Splitting requirements arbitrarily is a lose-lose compromise (Option C), postponing past the freeze is withdrawal (Option B), and mandating by seniority is forcing (Option D).
Question 2medium
On Day 4 of a two-week Scrum sprint, the VP of Marketing messages two backend developers directly asking them to build an unscheduled campaign-attribution export before Friday's executive webinar. The developers ask the project manager how to proceed. What should the project manager do FIRST?
- A.Ask the developers to work paid overtime this week so both sprint stories and the webinar export finish on Friday.
- B.Protect the active sprint and route the VP's request to the product owner for backlog prioritization.✓
- C.Extend the current two-week sprint by three extra business days to accommodate the VP's urgent export request.
- D.Log a formal baseline change request for next month's Change Control Board meeting before replying to the VP.
Correct answer: B
A servant leader shields the Scrum team from mid-sprint scope interruptions so sprint commitments remain protected while routing new stakeholder requests to the product owner, who owns backlog value and priority (Option B). Asking for overtime (Option A), stretching a fixed sprint timebox (Option C), and invoking a monthly predictive board (Option D) violate Agile principles.
Question 3easy
A newly assembled cross-functional Agile team experiences friction every morning because several developers open large pull requests five minutes before the daily standup, whereas QA engineers expect testable builds by mid-afternoon the prior day. Which action should the project manager take?
- A.Write strict daily code-cutoff rules personally and email disciplinary warnings for late pull requests.
- B.Facilitate a workshop for the team to co-create working agreements in the team charter.✓
- C.Separate developers and QA engineers into sequential two-week sprints so code handoffs happen once per month.
- D.Escalate the handoff friction to the functional engineering and QA directors to enforce department SLAs.
Correct answer: B
Ground rules and working agreements inside a team charter are most effective when co-created by the team itself so everyone commits to shared pull-request and review norms (Option B). Top-down edicts (Option A), premature escalation to functional managers (Option D), and reverting to sequential mini-waterfalls (Option C) weaken team ownership and flow.
Question 4medium
Over the past two sprints, escaped production defects have doubled, yet junior engineers say nothing during sprint retrospectives whenever the Director of Software Engineering attends as a silent observer. What should the project manager do FIRST?
- A.Cancel live sprint retrospectives altogether and rely solely on automated static code-quality metrics and dashboards.
- B.Require every junior engineer to submit signed root-cause defect explanations prior to each retrospective.
- C.Call on silent junior engineers randomly in front of the director so everyone speaks for two minutes.
- D.Ask the director privately to keep retrospectives core-team-only for psychological safety.✓
Correct answer: D
Sprint retrospectives require high psychological safety so the team can inspect mistakes candidly without fear of management evaluation; coaching the director privately to keep the ceremony limited to the core team removes the chilling effect (Option D). Signed blame reports (Option B), canceling retrospectives (Option A), and forced public spotlighting (Option C) worsen disengagement.
Question 5medium
A lead structural analyst who delivered flawless work for eight months on a predictive bridge-rehabilitation project has missed two consecutive calculation deadlines and replied curtly during weekly status calls. What should the project manager do FIRST?
- A.File a formal human-resources performance warning documenting the two missed deadlines and curt tone.
- B.Request an immediate replacement analyst from the functional engineering department to protect the critical path.
- C.Reassign the analyst's remaining structural work packages publicly during Friday's project status meeting.
- D.Hold a private, empathetic one-on-one conversation using active listening to uncover root causes.✓
Correct answer: D
Applying emotional intelligence starts with a private, non-judgmental conversation using active listening to understand whether hidden blockers, workload spikes, or personal stressors caused the sudden change (Option D). Requesting immediate replacement (Option B), filing formal HR warnings first (Option A), or reassigning tasks publicly (Option C) skips root-cause coaching.
Question 6hard
A distributed hybrid team spans Bengaluru, Munich, and Chicago across 11.5 hours of time-zone separation. Defect rework is climbing because sparse ticket notes cause overnight misunderstandings, while a rotating live all-hands daily standup forces one hub onto midnight calls every third week. Which solution BEST improves collaboration and sustainability?
- A.Prohibit cross-region collaboration on features so each city builds isolated components merged once per quarter.
- B.Pair short regional overlap handoff windows with recorded video summaries and explicit definition-of-ready ticket context.✓
- C.Route every technical clarification exclusively through the project manager as a central 24-hour message relay.
- D.Fix the daily all-hands standup permanently at Chicago's morning hour so meeting schedules remain predictable.
Correct answer: B
Distributed teams across wide time zones thrive when adjacent hubs use brief overlapping business-hour handoff windows reinforced by rich asynchronous video context and clear ticket readiness standards, eliminating midnight burnout (Option B). Permanent late-night calls for one site (Option D), quarterly siloed merges (Option A), and hub-and-spoke PM relaying (Option C) degrade morale and agility.
Question 7medium
On a predictive warehouse-automation rollout, the regional distribution manager holds high operational influence over shift supervisors. On the stakeholder engagement assessment matrix, she is currently 'Resistant'—worried handheld scanners will slow pallet loading—whereas project success requires her to be 'Supportive' before UAT next month. What should the project manager do NEXT?
- A.Ask the executive sponsor to mandate scanner adoption in the manager's annual performance appraisal.
- B.Send weekly mass-distribution newsletter updates explaining corporate return-on-investment targets for automation.
- C.Exclude her warehouse from initial UAT waves so testing proceeds solely with already supportive sites.
- D.Meet with her to explore loading-speed concerns and involve her supervisors in shaping UAT scenarios.✓
Correct answer: D
Moving an influential stakeholder from Resistant to Supportive requires two-way engagement: uncovering specific operational fears and co-designing UAT scenarios so her team validates real dock throughput firsthand (Option D). Executive coercion (Option A), excluding her site from testing (Option C), and generic ROI newsletters (Option B) fail to build genuine buy-in.
Question 8hard
In a balanced matrix organization, the functional Firmware Manager pulls an embedded-systems specialist off a hybrid cardiac-monitor project for 50% of the next three weeks to patch a legacy product line, jeopardizing a scheduled verification milestone. What should the project manager do FIRST?
- A.Meet with the Firmware Manager using impact data to negotiate shared timing or a peer backup.✓
- B.Submit an emergency baseline slip of three weeks to the sponsor without discussing alternatives first.
- C.Order the specialist to ignore the Firmware Manager's assignment and report full-time to the project war room.
- D.Hire an external staffing contractor immediately using unallocated project management reserve funds.
Correct answer: A
In a balanced matrix, resource authority is shared; the project manager should first collaborate directly with the functional manager, presenting objective milestone impact data to negotiate staggered allocation or an equivalently skilled resource (Option A). Issuing unilateral orders (Option C), conceding schedule slippage immediately (Option B), or spending management reserve alone (Option D) violates matrix governance.
Question 9medium
Midway through an Agile sprint, developers discover that an external mapping API deprecated a geocoding endpoint used in two active sprint stories. Three viable open-source SDK wrappers meet security standards, and the team asks the project manager to pick which SDK they must implement today. How should the project manager respond?
- A.Empower the developers to evaluate technical trade-offs and choose the SDK within project constraints.✓
- B.Instruct the product owner to dictate which open-source SDK wrapper the engineers must write against.
- C.Halt sprint coding until the Enterprise Architecture Board schedules a formal review next month.
- D.Select the SDK personally based on prior coding projects so developers spend zero time debating.
Correct answer: A
Self-organizing Agile teams own technical implementation ('how' to deliver sprint stories); when options already satisfy security and compliance guardrails, decentralizing the choice to the closest technical experts maximizes speed and accountability (Option A). Micromanaging the choice (Option D), stalling for a monthly board (Option C), or pushing technical selection onto the product owner (Option B) misaligns Agile roles.
Question 10hard
On a global hybrid logistics program, engineers in an offshore office with strong hierarchical cultural norms never question optimistic story-point estimates voiced first by onshore tech leads during live planning calls, yet silently miss sprint commitments afterward. How should the project manager adjust estimation practices?
- A.Adopt silent simultaneous Planning Poker voting before anyone speaks so estimates surface without anchoring or hierarchy bias.✓
- B.Confront offshore engineers publicly on the planning call whenever sprint velocity misses prior forecasts.
- C.Add a flat 40% padding buffer manually to every story assigned to the offshore engineering group.
- D.Instruct onshore tech leads to finalize all story-point estimates alone before sharing sprint assignments.
Correct answer: A
Simultaneous silent estimation (such as digital Planning Poker) prevents vocal senior leads from anchoring numbers first and creates a culturally safe mechanism for quieter or hierarchy-conscious engineers to surface complexity differences openly (Option A). Arbitrary management buffers (Option C), lead-only estimates (Option D), and public shaming (Option B) suppress honest sizing.